ENGINEERING TRACE
← Project studies

Foundation / quantity revision

One slab correction, three BOQ lines.

A revised model interpretation increased the measured slab concrete by 0.872 m³. The drawing issue and slab thickness stayed the same. The estimating team can reopen the concrete and mesh lines while it obtains rates.

Matched concrete elements
377
Measured BOQ lines changed
3
BOQ lines held
10

What changed in the model?

The earlier model used a diagonal boundary. The corrected outline follows the rectangle shown on the governing drawing. The slab remained 120 mm thick. Its net volume moved from 1.820 to 2.692 m³. The increase reconciles to the slab BOQ.

The BOQ revision

Net quantities, rounded to three decimals
ItemPreviousRevisedMovement
Slab concrete (m³)807.577808.448+0.872
Net bottom mesh area (m²)331.719338.984+7.265
Net mesh mass (kg)1,001.7911,023.732+21.941

All 26 source lines were compared. Thirteen measured lines retained their quantities. Ten lines carried incomplete or withheld quantities across both issues. The area and mass rows describe the same mesh. Select one contractual unit before pricing it.

What would this do to the estimate?

The issued BOQ contains no approved rates. For the measured slab line only, enter your own previous and revised rates to explore the effect. To isolate the geometry change, use the same rate twice.

Unpriced. Both rates are required for the comparison.Illustrative inputs. Calculated on unrounded measured volumes. Mesh, other BOQ lines, taxes and separate allowances are outside this example.

Decision for the estimator

Carry the revised quantity into the estimate. Obtain the applicable concrete rate and mesh pricing basis. Keep withheld items open. This change originated in the model interpretation. Any contractual instruction or entitlement requires separate evidence from the appointed parties.

Engineering Trace measures the issued information, prepares review models and BOQs, prices agreed scope and tracks revisions. The appointed designer retains design decisions, design verification and approval. The client or contractor authorises rates, procurement and contractual changes.

Earlier model summary (PDF) · Discuss a similar revision