Residential construction · Maysville, Missouri

Rosebud House

Which concrete quantity belongs in the estimate?

The reference plan shows a 32-foot house slab. The production CAD shows a 44-foot house foundation. Choosing the correct issue changes what an estimator measures.

See the 3D models and measured BOQ ↓
Two-storey Rosebud House with its attached garage, rendered from the project author's FreeCAD model.
Production model by Open Source Ecology. Engineering Trace adapted the view and materials. Credit & licence
Estimating decision

Use the production geometry for a model-based foundation allowance. Keep the earlier slab takeoff as a drawing check. Adding it to the foundation lines would count the same work twice.

Measure the house and garage separately

The SH4 production model supports two concrete lines. The earlier SH2 plan supports a separate slab and reinforcement study. The two issues answer different estimating questions.

The SH4 Revit federation opens in 3D. Its two linked models contain 70 structural-package elements and 1,847 architectural-context elements. Both links were reopened at their original coordinates.

Production house and garage in the federated Revit starting view.
SH4 · Whole-building coordination
Earlier slab, perimeter thickening and seven isolated carport piers.
SH2 · Reference foundations
Two perpendicular sets of native bars in the earlier reference slab.
SH2 · Isolated slab reinforcement

SH4 CAD by Open Source Ecology. Engineering Trace adapted the SH4 model view under CC BY-SA 4.0. SH2 views show a separate interpretation of the reference drawing.

BOQ item or checkQuantityMeasurement basis
SH4 house foundation10.477 m³Revit foundation family checked against the production solid.
SH4 garage foundation5.823 m³Separate family and BOQ line. The two production foundations total 16.300 m³.
SH2 uniform slab4.833 m³32 × 16 ft at 4 in thick. Earlier reference design.
SH2 perimeter thickening3.039 m³Nominal concrete below the slab. Check local threshold profiles.
SH2 slab reinforcement48 bars · 310.286 mNative #4 bars with illustrative ¾-inch end cover. Reopened geometry and scheduled length agree. The gross drawing allowance is 312.115 m before end deductions.
SH2 perimeter steel112.166 mFour nominal continuous #4 runs. Corner bars, laps and bent bars require detailing for fabrication.
SH2 carport piers7 supportsSix 16-inch and one 22-inch pier on the later markup. Depth and base profile remain open.

Estimate and revision

At the 2025 Maysville benchmark of US$118.95/yd³, the house allowance is US$1,630.06 and the garage allowance is US$905.98. Together they give US$2,536.04 for production foundation concrete. A current quote and its inclusions are still needed.

Across the two SH2 markups, all seven pier diameters decreased. The uniform slab stayed the same. Final pier quantities and a production reinforcement order require the applicable details.

Carry the two SH4 foundation lines into a preliminary estimate. Keep SH2 steel, local thickenings and carport supports on their own reference basis.
Download the one-page measurement brief (PDF)

Reference drawing · RB-SLAB-01

Follow one concrete line.

The slab is the simplest place to audit the method. Each step below refers to the same uniform layer in the earlier design.

  1. Drawing evidence32 × 16 ft

    Foundation plan S10, detail 1. Section S40, detail 2 gives a 4-inch standard layer.

  2. Model check4.833 m³

    One tagged IFC slab. Its reopened 3D geometry agrees with length × width × thickness.

  3. Measured BOQ6.321 yd³

    Gross uniform concrete across 512 ft². Edge beams and local thickenings require separate net measurement.

  4. Estimate at 2025 rateUS$751.88

    Unrounded quantity × US$118.95/yd³. A material allowance using the project's Maysville cost record.

Production CAD · Seed Eco-Home 4

What the built project's model contains.

Open Source Ecology published its house model. Engineering Trace extracted the two named foundation solids, checked that their surfaces enclosed a volume and measured both again after IFC export.

Production foundation takeoff at the historical rate
BOQ itemSource solidVolumeAllowance
House foundation RB-PROD-HFusion00613.704 yd³US$1,630.06
Garage foundation RB-PROD-GFusion0020997.617 yd³US$905.98
Foundation depth plan. The house measures 10.477 cubic metres and the garage 5.823. Dark outlines identify the thickened edges.
Revit 2024 schedules both foundations by BOQ key. Checking horizontal sections through the exported IFC confirmed the perimeter returns and the step where the garage meets the house.
Where does US$118.95 per cubic yard come from?

The 2025 Budget sheet records US$2,379 for “concrete - Maysville” and lists “20 yd.” We interpreted the unit as cubic yards and divided the recorded cost by 20. The separate Savannah purchase belongs to another property. The Maysville entry does not itemise delivery, tax or labour. These allowances use model volumes and a historical blended rate. A current bid needs a dated supplier quotation and agreed inclusions.

Why is the 32-foot slab kept separate?

The publisher identifies Seed Eco-Home 2 as the structural reference for Seed Eco-Home 4. We measured the production house foundation at 44 × 16 ft overall, including its full section. The earlier 32 × 16 ft takeoff covers only one uniform slab layer. An issued production drawing or site measurement would establish the installed dimensions. The 20-yard purchase alone cannot establish the installed volume.

Two issues of the same drawing · S10

Seven pier positions stayed. Their diameters changed.

Carry the slab quantity forward.

Markups 3 and 4 are dated 29 September and 21 October 2022. Both show the same house slab dimensions. At a fixed rate the change to the uniform slab line is US$0.

Hold the pier price.

Six carport piers changed from 22 to 16 inches in diameter. One changed from 28 to 22 inches. S40 shows straight and belled alternatives. Confirm the selected detail and governing depth before pricing the change.

Where the seven separate foundations belong

The SH2 plan shows seven isolated carport piers. The six outer supports and one larger middle support each have a unique record. S40 specifies a minimum embedment of 36 inches and permits a bell-bottom option. The final pour volume depends on the selected profile and actual depth.

Six 16-inch carport piers and one 22-inch middle pier on SH2 markup 4.
Engineering Trace diagram based on S10, markup 4. The earlier markup shows six 22-inch and one 28-inch pier.

Concrete and reinforcement coverage

The production garage has its own modelled foundation at 5.823 m³. On the separate SH2 reference plan, four perimeter grade beams surround the house slab. A short bearing strip sits inside it. The takeoff records the slab, edge and interior thickenings, thresholds, corner bars, bent bars and pier details individually.

The slab detail calls for bottom #4 bars at 12 inches each way. The exterior footing detail shows two #4 bars at the top and two at the bottom. A final steel weight requires the applicable production reinforcement details and cutting lengths.

Evidence and authorship

Rosebud is an independent measurement study of Open Source Ecology's completed home. The whole-house Revit 2024 model brings together 1,915 credited CAD reference components and two foundations authored by Engineering Trace. The two native foundation schedule rows agree with the source geometry and IFC4 export. The full-house Navisworks review was saved and reopened. All 1,917 production component keys were located, including the house and garage foundations. The priced scope covers foundation concrete. The earlier reference slab has its own takeoff.